Construction of Cernavoda's 3 and 4 reactors to be ready no earlier than 2016, investors say
Reactors 3 and 4 of Romania's sole nuclear plant in Cernavoda will be delivered in 2016 the earliest and not in 2015 as it had been estimated, declared for NewsIn the representatives of the companies involved in the project.
The actual construction of the two units will be started 18 months from registering the managing company, probably in 2010, according to representatives of Nuclearelectrica, who added that six more years will have to pass before the reactors are started.
"We hope to finalize the two units in 2016. But, if things do not go
according to plan, the project could also be delayed until 2017," they
said.
CEZ Romania, another investor in the construction of the two units,
alsoanticipates reactors 3 and 4 in Cernavoda could be delivered in
2016.
"The managing company will finish the feasibility study in 2010 and will immediately start the actual construction process," declared for NewsIn the corporate affairs director of CEZ Romania, Adrian Borotea.
The state-owned electricity producer Nuclearelectrica inked a deal on
November 20 2008 with six investors, ArcelorMittal, CEZ, GdF-Suez,
Enel, Iberdrola and RWE Power, to form the SC EnergoNuclear SA company
managing the construction of the 3 and 4 reactors at the country's sole
nuclear power station.
Nuclearelectrica, which is in charge of supervising the plant, will
hold 51 percent of the project, four of the companies will have a
participation of 9.15 percent and two companies a 6.2 percent stake
each.
The additional 3 and 4 Cernavoda reactors will have an installed power
of 720MW. The life span of a reactor is 30 years with the possibility
of extension to 40 years. The 3 and 4 Cernavoda units will use Candu 6
technology.